Tidbits from the Top

Two Week Schedule

A new schedule is created every Friday that projects the next two weeks of building.  There are many factors that can alter scheduling including weather, material delays, crew speed, tool/equipment failures, vehicle problems and labor issues to name a few.  We find it best to attempt to layout jobs for a two week stretch to minimize the guessing that would have to be done to figure out further.  Jobs outside the two-week schedule are in a queue and remain in the order they entered the queue until they are placed on the schedule. 

Jamie Bird

Jamie Bird

Owner, General Manager, CEO, CFO

All our tidbits come directly from the top. Sharing our knowledge and processes with consumers as accurately as possible is what we strive for. The fewer people that information gets passed through, the more accurate it is!