We do everything possible to keep this information current; however, there are circumstances that may cause the schedule to change at any moment. The schedule can be affected by many things, including but not limited to, weather, equipment failure, illness, receipt of materials, etc. We understand that our customers may be coordinating different phases of the job on their own; therefore, we rely on you to keep us informed as to when these phases have been completed and you are ready for us to proceed. Economy Garages strives to meet the following Job Completion Guidelines.

1. Permit – applied for within 1 week of acceptance of your contract and receipt of the downpayment.

2. Ground Preparation – within 2 weeks from the date of receipt of your permit, receipt of all necessary progress payments, and notification from you that your removals have been completed, if applicable. During spring months, scheduling may be affected by road restrictions put in place by the Minnesota or Wisconsin Departments of Transportation. During the winter months, scheduling may be affected by cold temperatures creating frost which would require use of our ground heating system to proceed.

3. Concrete – within 3 weeks of completion of the ground preparation or notification from you that your ground preparation has been completed, if applicable. During the winter months, scheduling may be affected by cold temperatures creating frost which would require use of our ground heating system

4. Concrete Block (1 – 2 courses) – within 1 week of completion of the concrete slab.

5. Concrete Block (more than 2 courses) – within 2 weeks of completion of the concrete slab.

6. Building (May- September) – to begin within 3 weeks of the completion of the concrete and receipt of all required progress payments, notification from you that your concrete work has been completed and receipt of all building materials, if applicable.

7. Building (October – April) – to begin within 4 weeks of the completion of the concrete and receipt of all required progress payments, notification from you that your concrete work has been completed and receipt of all building materials, if applicable.